By Anthony Kitimo
Four years after Mombasa County Assembly approved plans to desalinate seawater, to help address an acute water shortage facing the county, the project remains stuck at preparation stage.
The Sh16 billion desalination plants, one to be based in north mainland at Shimo La Tewa and the other in the south, in Likoni constituency have failed to kick off due to lack of letter of comfort.
According to Mombasa Water Supply and Sanitation Company (Mowasco) managing director Anthony Njaramba, the two plants are to supplement the current water sources and were touted to be a solution to the perennial water shortage facing Mombasa County.
“The projects are currently at preparation stage and they are delaying because of lack of letter of comfort,” he said.
Read Also
DESALINATION PLANT CLOSER TO REALITY AFTER COUNTY ALLOCATED LAND
SOLAR-POWERED WATER TREATMENT PLANT INSTALLED AT MTWAPA KENYA
WATER SHORTAGE IN TAITA TAVETA COUNTY IS MAN MADE
SICILY TO COMMISSION MZIMA II WATER PROJECT IN TWO WEEKS
Letter of comfort is an official communication from a party to a contract to the other party that indicates an initial willingness to enter into a contractual obligation absent the elements of a legally enforceable contract.
Mr Njaramba said once the documentation is complete, the two projects should begin and will cover the 130,000 cubic meters shortage the county experiences daily.
The MD said once the documentation is complete, the construction of Shimo La Tewa plant is expected start and will take between 12 to 24 months to be complete.
“Mombasa gets an average of 30,000 cubic meters against a demand of 200,000 and desalination plants, Mwache dam project and the Mzima Spring II will ensure water shortage problem is solved,” said Mr Njaramba.
The national government is in the process to expedite the implementation of the Sh42 billion Mzima Springs II pipeline and Mwache Dam projects.
In August 2018, Mombasa County Assembly passed a motion proposing the construction of two desalination plants and later governor Hassan Joho’s administration awarded Almar Water Solutions of Spain and Switzerland’s Aqua Swiss tender to construct the two plants.
Aqua Swiss was awarded a contract to build a smaller desalination plant in Likoni that can purify 30,000 cubic metres per day while Almar Water Solutions will put up the desalination plant in the north of the mainland at Shimo la Tewa.
President Uhuru Kenyatta approved acquisition of more than 10 acres at the Shimo La Tewa Secondary School for the desalination plant.
The move gave impetus to governor Joho’s plan to purify Indian Ocean water for use by the residents and to address the perennial water shortages in Mombasa, and the huge demand in neighbouring Kilifi County.
The county has been experiencing acute shortages due to reduction of supply from Baricho Dam in Kilifi, Mzima Springs in Taita-Taveta and Marere Springs in Kwale.
Mombasa lacks a fresh water source and the supply from Mzima Springs has been declining leading to residents, industries, and businesses to contend with dry taps for months.
Acute water shortage in Mombasa has also been attributed to direct theft of no-revenue water and illegal connections.
more recommended stories
THE GOVERNOR DISCOVERS FISCAL DISCIPLINE — FOUR YEARS TOO LATE?Perhaps one of the most.
SHAKAHOLA: 200 YEARS FOR MACKENZIE, BUT WHO WILL ANSWER FOR THE STATE’S FAILURE?Kwaela News Network | Editorial.
WHO IS THIS GOVERNOR TAITA-TAVETA COUNTY IS LOOKING FOR BEYOND 2027?As the 2027 General Election.
COURT HALTS COAST WATER DISCONNECTIONS AS EJF CHALLENGES SH6 BILLION DEBT CLAIMKwale, 29 August 2026 —.
THE LEGENDARY 70-YEAR-OLD MZIMA PIPELINE LIVES TO BURST ANOTHER DAYGovernment Celebrates Repairing What It Failed.
TRAGIC LOSS OF JOHN KALAGHE JOSHUA LEAVES FAMILY AND COMMUNITY IN MOURNINGIt is with profound sorrow and.
THE NAIROBI–MOMBASA EXPRESSWAY: A DECADE OF PROMISES, YET NO HIGHWAY IN SIGHTThe Highway That Exists Only.
FROM FUEL TO DRINKING WATER: HOW A BILLION-SHILLING PIPELINE DREAM RAN AGROUNDA Lesson in Why Politics Should.
LIKONI BRIDGE: WHAT HAPPENED TO RUTO’S KSH 100 BILLION PROMISE?For years, residents of Mombasa and.
MZIMA PHASE TWO: SIX DECADES OF PROMISES, DELAYS AND GOVERNMENT FAILURECoast Residents Continue to Suffer as.
ABSENT LEADERSHIP OR CALCULATED DISRESPECT? QUESTIONS MOUNT OVER KINGI’S NO-SHOW AT MGANGE NYIKA FUNDRAISER.Serious questions are emerging following the.
ATHANAS MBELE’S “BIG 7 AGENDA” VISION POSITIONS WUNDANYI FOR TRANSFORMATIONAL GROWTHWundanyi is emerging at the center.
POLITICS ON OVERDRIVEKenya is not a permanent.
WHY TAITA TAVETA NEEDS ITS OWN POLITICAL VEHICLEBy Geoffrey Kimonge (GK) The Case.
HAS GREED CONSUMED THE TAITA TAVETA COUNTY ASSEMBLY?By Geoffrey Kimonge (GK) Has the.
THE COLLAPSE OF PAA: AMASON KINGI’S POLITICAL HOLLOWING EXPOSED IN MAGARINI AND TAITA TAVETABy any political measure, Pamoja.

Leave a Comment